Manufacturing company2025Role: Turnaround co-lead

A resource model that became the replan

A large SAP program was six months behind. I was brought in to help reset it, and built the model the program ended up running on.

6 months
behind schedule when I joined
10+
workstreams in one bottom-up plan
Oct 2025
go-live reached
The problem

The program had more than 3,000 Jira issues and 10+ workstreams, from order-to-cash to reporting. No one could say whether the plan was feasible, because no one could see who was overbooked and who had room.

Without that view, every replan was a negotiation of opinions.

How it works

Plan and people in, weekly capacity out

Scroll sideways to see the full diagram →
Fig. 1The model put demand and capacity on one chart, so the replan became a matter of moving work, not arguing about it. The heatmap values are illustrative.
What I did
  • Co-led the reset with a firm partner, and ran the program-wide replan meetings that won the client's buy-in.
  • Built the Python and Alteryx allocation model, and walked the client's program office through how it works.
  • Built a Jira dashboard showing the critical path by workstream. The firm later reused it as a reference for another client.
  • Wrote Python checks for duplicates, blanks and mismatches in product master data, tied to an issue that touched about 440,000 records.
  • Led executive escalations, and ran daily status and defect triage through the third integration test cycle.
Outcome

The model became the live replan, and the program reached go-live in October 2025. The client's CIO asked for me to stay on the program.

PythonAlteryxJiraCapacity planningExecutive alignment